Renew atlanta and TSPLOST Review of expenditures - December 2018
Renew Atlanta and TSPLOST—Review of Expenditures
Released December 2018 Download the Full Report here We undertook this audit pursuant to City Council's request in resolution 18-R-3297. Our objectives were to answer the following questions:
|
We found that as of July 31, 2018:
- A plurality of Renew Atlanta projects were in close out; 54% were either under construction or in close out
- 65% of Renew Atlanta funds had been spent or encumbered
- The Renew Atlanta Bond premium supplemented other projects and funded work by our office
- 63% of active TSPLOST projects were in construction procurement
- 9% of possible TSPLOST funds had been spent or encumbered
- 205 out of 228 legislated Renew Atlanta projects were on the active project list
- Changes to project lists appeared consistent with requirements
- Oracle records and Renew Atlanta/TPSLOST records reconciled, which was an improvement from inconsistencies found in our earlier audit